October 19,2009
Peruvian Copper
Projects to $5.1 Billion
Giant
miner
Xstrata plc
(LON:XTA) (Zug, Switzerland) (LSE: XTA.L) announced major investments in the
company's Peruvian copper mine projects, Las Bambas and Antapaccay, at the 29th
Perumin - Convencion Minera, one of the most important mining conventions in
Latin America, last month in Arequipa, Peru. Las Bambas is now expected to be
worth $3.8 billion and Antapaccay is expected to be worth $1.3 billion, totaling
$5.1 billion; previously, the two were thought to be worth $2.2 billion.
The Las Bambas project entails the construction of an open-pit mine and a
140,000-ton-per-day concentrator plant with two grinding lines. Mining
operations are expected to produce 324,000 tons per year of copper, and 4,600
tons of molybdenum during a mine's life of 18 years. Las Bambas is in the city
of Cotabambas, in the Apurimac region, some 150 kilometers from the Xstrata's
fully owned and operational Tintaya mine. The company expects to complete a
feasibility study in December and to present the environmental impact assessment
to the Peruvian Authorities in mid-2010. Construction is expected to start at
the end of 2011, with project completion set for the second quarter of 2014.
The Antapaccay project entails a smaller mining operation, with an open-pit mine
and a 70,000-ton-per-year concentrator plant with one grinding line, designed to
produce 160,000 tons per year of copper over 22 years. Antapaccay is just 12
kilometers from the Tintaya mine and is also known as the Tintaya mine expansion
project. Tintaya is expected to close operations during 2013, when Antapaccay
mine will be operational. The economic evaluation stage is being completed in
the next few weeks and the construction is planned to start at the end of 2010.
Bechtel Chile Limited (Santiago, Chile) is in charge of the feasibility studies
for both projects.
Xstrata operates both projects though subsidiary Xstrata Peru S.A. (Arequipa,
Peru). Also in Peru, Xstrata owns 33.75% interest in the joint-venture Compania
Minera Antamina S. A., which operates the open-pit Antamina copper-zinc mine.
October 18,2009
Chinas Power
Consumption Increases 10.42%
From
January to September, China's overall social power consumption reached 2,663.55
billion kWh, a 1.4% increase compared with the same period in 2008. Of that
amount, power consumption in the first industry reached 72.46 billion kWh, a
6.35% increase; consumption in the second industry reached 1,954.94 billion kWh,
a 1.67% drop; consumption in the third industry reached 293.50 billion kWh, an
11.26% increase; and consumption in the household of urban and township
residents reached 342.65 billion kWh, up 11.73% year over year.
From January to September, the overall power consumption of industry reached
1,927.26 billion kWh, a 1.8% drop year over year. Of that amount, the growth in
light and heavy industry dropped 2.74% and 1.6%, respectively.
There are a total of 17 provinces and regions with increases above the national
average level (1.4%). Xinjiang jumped to the top in the rankings (9.9%),
followed by Jiangxi (7.95%), Hainan (7.87%), Anhui (7.57%),Yunnan (7.25%), Hunan
(6.63%), Hebei (6.41), Beijing (5.25%), Chongqing (5.11%), Sichuan (4.02%),
Guangxi (3.81%), Guizhou (3.71%), Shandong (3.23%), Fujian (2.44%),
Tianjin(2.03%), Zhejiang (1.92%) and Hubei (1.67%).
From January to September, the national investment in power source projects
reached $29.15 billion. (The investment in power source projects from January to
August was corrected to $24.85 billion). As of the end of September 2008, the
total installed capacity of power plants of 6 MW or more in China reached 800.18
million kW, a 9.2% increase year over year. Of that amount, installed capacity
of hydropower reached 155.51 million kW, a 14.1% increase; thermal power reached
622.03 million kW, a 7.2% increase; nuclear power reached 9.08 million kW,
remaining at the same level; and wind power reached 13.33 million kW, an 88.8%
increase.
From January to September, the average accumulated utilization of power
generation equipment in China reached 3,352 hours, a drop of 283 hours year over
year. Of that amount, the average utilization hour of hydropower equipment
reached 2,671 hours, a drop of 180 hours year over year; and the average
utilization hour of thermal power equipment reached 3,515 hours, a drop of 284
hours year over year. From January to September, the average coal consumption in
power supply reached 341 grams per kWh, a drop of 6 grams per kWh year over
year; the accumulated plant service power consumption rate reached 5.88%, of
which hydropower was 0.60% and thermal power was 6.68%; and line-loss rate
reached 6.21%, an increase of 0.24% year over year.
October 16,2009
CCGT Plant for U.K.
E.ON UK (Coventry, England), part
of German energy giant
E.ON AG (OTC:EONGY) (Dusseldorf,
Germany), has revealed plans to build a 1,600-megawatt (MW) combined-cycle
gas-turbine (CCGT)
power station in High
Marnham, in Nottinghamshire, England.
The project is in the very early stages. E.ON is currently seeking public
feedback about the project, but the energy giant is looking to submit a planning
application early next year. If successful, the 1,600-MW plant will be up and
running by 2018, generating enough electricity for up to 2 million homes and
businesses. The plant will be constructed on the site of the old High Marnham
coal-fired plant, a 945-MW facility that was mothballed in 2003 after more than
40 years of service.
Andy Burnett, E.ON's project development manager, said: "We're looking to secure
the option to develop a power station at High Marnham that will help ensure we
can keep the lights on for our homes and businesses in the most secure and
affordable way, while also helping to tackle the global threat of climate
change. If built, the new plant could produce power for over two million homes
and would bring a range of opportunities for local people and businesses in
terms of jobs and services that would be required during construction and
beyond."
E.ON has submitted a request for "scoping opinion" to the Department for Energy
and Climate Change (DECC), Nottinghamshire County Council, Bassetlaw District
Council, and a number of other statutory consultees. Public opinion could play a
key role in getting permission for the new plant, as getting the green light and
securing funding for new fossil-fuel plants are becoming increasingly difficult.
E.ON has already announced that it has postponed plans for the controversial
Kingsnorth coal-fired plant in Essex, while
Dong Energy (Skaerbaek,
Denmark) has pulled out of a project to build the 2.14 billion euro Hunterston
on the Clyde coal-fired plant with Peel Energy (Manchester, United Kingdom). For
additional information, see news items from October 12 and 15, 2009 -
E.ON Shelves £1.5 Billion Kingsnorth Coal-Fired Plant
Replacement and
Dong Energy Cancels Two Coal-Fired Projects.
Burnett added: "We're very proud of the relationships we have in our local
communities, so while it's still very early days, we're absolutely committed to
talking to everyone so they can ask any questions they may have."
E.ON hopes to obtain permission for the project, as in nearby West Burton, rival
EDF Energy, the U.K. arm of French utility
Electricite de France SA
(EPA:EDF) (Paris), is constructing a 1,300-MW gas-fired plant next to the
existing 2,000-MW coal-fired plant. Work commenced in January 2008, and the
power station will be ready for commercial operation in 2011 with an expected
life of 25 years. Once completed, the CCGT plant will generate enough power for
1.5 million homes.
October 15,2009
India's L&T Plans 5000
Megawatts
Indian
engineering and construction major,
Larsen & Toubro Limited
(BSE:500510) (L&T) (Mumbai) is reportedly considering a foray into the
power
generation sector, with plans to invest in 1,000 megawatts (MW) to 2,000 MW of
power generation capacity in the coming years, and eventually expand to an
overall generating capacity of 5,000 MW in a period of five years thereafter.
The Indian government has committed to investing $12.3 billion in the power
generation and transmission sectors this fiscal year. L&T expects to win orders
worth more than $2.2 billion in power generation projects this year. The firm is
also optimistic about securing orders in the power transmission business, which
accounts for about 75% of the revenue and 70% of the operating income of L&T's
Engineering, Construction and Contracts (ECC) division. India is expected to
invest $10 billion during the next five years in enhancing the country's
transmission network.
L&T's foray into the power generation business began in January 2005, when it
announced plans to develop a 400-MW power plant at Uttaran, near Surat in
Gujarat, with an investment of nearly $260 million. The project marked the
firm's first venture in developing a power plant, although the firm had been
providing engineering, procurement and construction services to developers of
power plants and distribution and transmission infrastructure. L&T also
announced plans to foray into the power distribution and transmission businesses
after attaining financial closure for the Uttaran power project, then expected
in January 2006. The project was executed by L&T's ECC division. L&T also
indicated that it would float a new special purpose vehicle to handle the new
business segment.
In July 2007, L&T announced a significant restructuring of businesses, under
which L&T Power Projects Limited (L&T PPL) and L&T Power Development Company
Limited (L&T PDC) were formed. L&T PPL was designed to be the investment arm for
all the group's thermal, hydro and nuclear power projects, while L&T PDC would
execute coal-fired and multi-fuel power plants. L&T PPL also was entrusted with
the group's ventures in the power transmission and distribution sectors.
At the time, L&T announced plans to develop coal-based power generating
capacities of up to 5,000 MW during a period of five years, with a total
investment of $4.3 billion. The venture was to be funded in a debt-to-equity
ratio of 70:30, with L&T investing $1.3 billion and raising the balance funds
through debt. L&T also planned to bid for ultra-mega power projects through its
power subsidiary.
In June 2008, L&T revised investment plans for power generation projects. While
the target of developing 5,000 MW of power generating capacity during a period
of five years remained unchanged, the overall investment envisaged rose to $5.4
billion, and the firm planned to fund the initiative in a debt-to-equity ratio
of 80:20, with L&T investing $1.08 billion and raising the balance funds
required through debt.
Last month, L&T secured a $430 million contract from GMR Energy Limited
(Bangalore, Karnataka) to develop a gas-based power plant at Vemagiri near
Rajahmundry in Andhra Pradesh. The power plant will comprise two units of 384 MW
each and will be developed on a lump sum turnkey basis by the end of March 2012.
L&T also secured a contract last month from the state government of Himachal
Pradesh to develop the 149-MW Sach Pass hydropower project. The firm is
developing the $108 million, 60-MW Singoli Bhatwari hydroelectric power project
on the Mandakini River, under a contract secured in May 2006 from the state
government of Uttaranchal. L&T is executing the contract on a
build-own-operate-transfer basis and will operate the power plant for 45 years.
The firm also will develop a 12-kilometer, 132-kilovolt transmission line as
part of the project.
With more than four decades of experience in the power sector by way of
providing engineering, procurement and construction services and undertaking
civil, electrical, mechanical, and instrumentation works, L&T has participated
in more than 100 power projects with a combined generation capacity of 35,000
MW. The firm is looking to tap into opportunities present in India's burgeoning
power sector through a foray into the power generation segment.
October 08,2009
Italian IES Refinery
Researched by Industrial Info Resources (Sugar Land, Texas)--The
51,000-barrel-per-day (BBL/d) IES
refinery, located in
Mantova in the region of Lombardy, Italy, is scheduled to perform a maintenance
shutdown in November. The refiney is owned by
MOL Hungarian Oil and Gas plc
(Budapest, Hungary).
The shutdown is planned to start November 2, and units are expected to be
brought online November 28. Although maintenance will take place in the Topping,
the 24,000-BBL/d Visbreaking, the Vacuum, the 8,900-BBL/d Thermal Cracker, and
the MildHydrocracking, the entire facility will have to be brought offline
because the plant has only one production train. Cestaro Rossi & c. SpA (Bari,
Italy) and Ais are in charge of the turnaround. Both companies have worked with
the refinery for a long time.
The next planned maintenace turnaround is scheduled to take place in the fourth
quarter of 2010, and the next overhaul in the fourth quarter of 2012.
The refinery has a potential storage capacity of 8,000 tons per day, and refines
petroleum mainly from Syria, Egypt, Russia, Iran and Iraq.
October 07,2009
2010
Capitol Spending.
Researched by Industrial Info Resources (Sugar Land, Texas)--Because of the
recession, the
Oil & Gas Transmission Industry
has been going through an adjustment period or global reset of sorts. In 2009,
economics, combined withregulatory and funding issues, forced many companies to
place projects on hold, delay spending or cancel projects entirely. Project
owners are re-evaluating projects and trying to reduce costs where possible.
Against such a backdrop, one might expect a pessimistic outlook, but certain
sectors show promising signs for a positive 2010 as far as capital spending is
concerned. Some of the more positive sectors include shale gas developments such
as the Barnett Shale, which are attracting increased pipeline infrastructure
construction, as well as CO2 pipeline construction.
Join Ilna Penny, Senior Pipeline Analyst for Industrial Info, as she explores
these developments on this week's "Navigating the Currents of Change" webcast.
Industrial Info Resources (IIR) is the leading provider of global market
intelligence specializing in the industrial process, heavy manufacturing and
energy related markets. For more than 26 years, Industrial Info has provided
plant and project opportunity databases, market forecasts, high resolution maps,
and daily industry news.
.
September 22,2009
BP Sells Indian Wind
Assets
Researched by Industrial Info Resources (Sugar Land, Texas)--BP
plc (NYSE:BP) (London, England) has divested
the company's wind
power assets in India
with the sale of BP Energy India Private Limited (BPEIPL) to independent power
producer Green Infra Limited for $95 million. The equity component of the sale
amounts to $37 million, while the debt component amounts to $58 million.
The transaction was a result of a strategic decision taken by BP to focus on
offshore wind development projects in the United States, where its wind energy
portfolio consists of nearly 100 projects with a combined potential
power-generating capacity of more than 20,000 megawatts (MW).
With the acquisition of BPEIPL's assets, comprising three wind power plants with
a total capacity of 100 MW, Green Infra is the largest independent power
producer in India's renewable energy sector with a total capacity of 124 MW.
BPEIPL owns and operates a windfarm in Maharashtra and two wind power projects
in Karnataka. The 40-MW windfarm in Dhule, Maharashtra, commenced operations in
the second half of 2007. The 36.3-MW wind power plant in Bharmasagara,
Karnataka, was commissioned in the last quarter of 2008, while the 23.1-MW
windfarm in Telagi, also in Karnataka, was commissioned in the first quarter of
this year. Green Infra operates a 25-MW windfarm in the southern Indian state of
Tamil Nadu.
Green Infra is a joint venture between IDFC Private Equity (IDFC PE) (Mumbai), a
wholly owned subsidiary of
Infrastructure Development Finance Company Limited
(BSE:532659) (IDFC) (Chennai, Tamil Nadu) that is India's largest private equity
fund focused on the infrastructure sector, and Emergent Ventures India (Gurgaon,
Haryana), which provides advisory services in Clean Development Mechanism (CDM).
Green Infra has 100% equity support from IDFC PE, which has committed funds of
about $75 million, of which more than $41 million already has been disbursed to
the independent power producer and includes the equity component entailed in the
recent transaction with BP.
The acquisition of BPEIPL is in line with Green Infra's plans to invest $623
million in 500 MW of renewable power-generation projects across the country by
the end of the 11th five-year plan period, 2007-12. According to plans announced
by the firm in April, about 300 MW of the proposed capacity would be generated
from wind power plants, 100 MW from small-sized solar power projects, and the
remainder from small-sized, gas-based and biomass power plants. The overall cost
of developing the proposed renewable-power projects is estimated at $1.25
million per MW of installed capacity.
Green Infra operates assets worth more than $155 million, including a project
development pipeline of more than 300 MW, as well as 20 MW of assets eligible
for generation-based incentives awarded by the Indian government. The firm plans
to pursue organic as well as inorganic growth through further acquisitions. IDFC
PE estimates that only 7.5% of India's estimated potential in generation of
renewable energy has been harnessed so far. The firm also intends to focus on
the development of onshore windfarms, which are less expensive than offshore
wind power projects.
According to a recent publication titled "Indian Wind Energy Outlook 2009,"
released jointly by Global Wind Energy Council (Brussels, Belgium) and Indian
Wind Turbine Manufacturers Association (Chennai, Tamil Nadu), wind power is
expected to address up to 24% of India's power requirements and generate 213,000
green-collar employment opportunities by the year 2030. The sector is expected
to attract annual investments of about $9.86 billion during this period.
BP clarified that the sale of its wind assets in India would have no impact on
other businesses conducted by the firm in the region. The firm holds a 71% stake
in leading automotive lubricant producer Castrol India Limited (BSE:500870)
(Mumbai). BP owns a coal-bed methane block in Birbhum, West Bengal, and a
deepwater-gas exploration block in the Krishna-Godavari basin. The firm also has
been operating
Tata BP Solar India Limited
(New Delhi) as a joint venture between BP Solar International Incorporated
(Frederick, Maryland) and
Tata Group (Mumbai) since
1989. The venture manufactures solar cells, photovoltaic modules and solar
thermal systems, and exports about 60% of its products primarily to Europe.
In the U.S., BP has interests in six windfarms with a total installed capacity
of more than 1,000 MW, and an additional 1,000 MW of wind power projects that
are in advanced stages of development. The firm operates the Fowler Ridge I
project in Indiana, with a capacity of 400 MW; the Cedar Creek windfarm in
Colorado, with a capacity of 300.5 MW; the Sherbino I project in Texas, with a
capacity of 150 MW; the Flat Ridge I windfarm in Kansas, with a capacity of 100
MW; the Silver Star I windfarm in Texas, with a capacity of 60 MW; and the Edom
Hill wind power project in California, with a capacity of 20 MW.
(there are no exact PEC matches with US windfarms above. There are PECS for new
BP projects and expansions)
September 15,2009
Siemens Energy Secures
$132 Million
Researched by Industrial Info Resources (Sugar Land, Texas)--Siemens Energy (Erlangen,
Germany), a subsidiary of
Siemens AG (NYSE:SI)
(Munich, Germany), recently secured an order valued at $132 million from OOO RN-Tuapsinskiy
NPZ, a subsidiary of
NK Rosneft OAO (LSE:ROSN)
(Moscow, Russia), for the supply of six industrial gas turbines and generators
for generation of steam and
electricity as part of
the expansion of Rosneft's Tuapse
refinery on the Black Sea
coast in the Krasnodar territory of southern Russia.
Siemens Energy will supply six SGT-800 gas turbine units of 47 megawatts (MW)
each. Three units will be delivered in the latter half of 2010, while the
remaining three units are scheduled for delivery by the end of 2012.
RN-Tuapsinskiy is undertaking expansion and upgrading projects to augment the
refining capacity of the Tuapse facility from about 110,000 barrels per day
(BBL/d) to about 250,000 BBL/d. The refining depth will be enhanced from 56% to
95%, and the upgrade project will allow the refinery to produce products
compliant to Euro-4 and Euro-5 standards.
Commissioned in 1929, the Tuapse refinery is Rosneft's oldest refinery and the
only Russian refinery located on the Black Sea coast. The facility specializes
in the production of motor fuel. Crude oil feedstock for the refinery is
procured from western Siberia through the Transneft pipeline system and from
Rosneft's oilfields in southern Russia through the pipeline and by rail. Located
near the Tuapse oil-loading terminal, the refinery exports nearly 90% of its
petroleum products, while the remainder is sold in the domestic market. In 2008,
the refinery processed 110,000 BBL/d of crude oil and had an output of 5.11
million tons of petroleum products. Output from the refinery comprised 2.26
million tons of fuel oil, 1.7 million tons of diesel fuel, 1.02 million tons of
gasoline and naphtha, and 60,000 tons of other petroleum products.
Upon completion of the expansion and modernization program, the Tuapse refinery
is expected to fully cater to the demand for high-quality fuel in the Southern
Federal District of Russia. In addition, the Tuapse oil-loading terminal is
being upgraded to a trans-shipment capacity of 17 million tons per year, which
will augment exports from the refinery.
Siemens Energy previously supplied three SGT-800 turbines of 45 MW each to
Rosneft for the development of a 135-MW gas-turbine power plant at the
Priobskoye oil deposit in Siberia. Awarded in April 2008, the contract was
valued at more than $58 million. The power plant was to be developed in three
stages, with the three SGT-800 units to be used in the first 135-MW stage, which
was scheduled for commissioning in December 2008. The second and third stages
were scheduled to go on stream in December 2009 and April 2010, respectively. In
a more recent press release, Siemens reports having received orders from Rosneft
for a total of seven SGT-800 turbine units for the power plant. With a power
generation capacity of 315 MW, the plant will cater to the power requirements of
Rosneft's facilities associated with the oilfield. The facility will operate on
a feedstock of petroleum gas and is part of Rosneft's strategy to increase the
utilization of associated gas produced in the oil field.
Siemens Energy also supplied three SGT-800 turbine generator units to the
Kolomenskoe combined heat and power (CHP) plant in Moscow, which commenced
operations in June this year. The facility has an overall efficiency of 83% and
supplies 136 MW of electric power and 171 million kilocalories per hour of
district heat to Moscow. The power plant was constructed by NaftaSib Energiya
OOO (Moscow) under a contract with the government of Moscow.
In January this year, Siemens Energy supplied two SGT-800 gas turbines as part
of a $147 million equipment supply contract placed by OJSC Territorial
Generating Company #9 for the development of a CHP plant in Perm in the Volga
federal district. The project is part of the reconstruction of a 60-year-old CHP
plant in the region and is aimed at increasing the thermal capacity of the
facility from 57 MW to 180 MW. The new CHP plant is scheduled to go online in
2010.
The SGT-800 unit was launched in 1997 under the name GTX100 and had a power
rating of 43 MW. The power rating in simple-cycle applications was subsequently
increased to 45 MW and more recently to 47 MW. Electrical efficiency increased
from 37% to 37.5%. (In combined cycle power plants, output has increased from 64
MW to 66 MW, and efficiency has increased from 53% to 54%.) The unit offers
several benefits, including high efficiency, high reliability, low
lifecycle-costs, and operability under extreme climatic conditions. Capable of
operating on a variety of fuels including liquid fuel, natural gas, and dual
fuel as feedstock, each unit is also equipped with a Dry Low Emissions
combustion system that minimizes emissions of nitrogen oxides under a range of
operating conditions. To date, Siemens has fulfilled or is currently executing
orders for the supply of 29 SGT-800 units to Russia.
September 15,2009
Siif Energies do Brasil
Researched
by Industrial Info Resources (Sugar Land, Texas)--Siif Énergies do Brasil (Fortaleza,
Brazil), a company that specializes in developing
wind power projects,
formally inaugurated its 105-megawatt (MW) Praia Formosa windfarm last September
10 in Camocim, a resort town in the northeastern state of Ceará.
The windfarm began operations the last week of August, when units were
commissioned after being granted approval by the federal energy authority (ANEEL).
The windfarm consists of 50 Sulzon S88 wind turbines, with a nominal capacity of
2.1 MW each.
With a total investment of $276.86 millon, Praia Formosa has become the biggest
windfarm in northeastern Brazil, making Ceará the leading state regarding
windpower generation. The windfarm, as with many others across the country, was
built under incentives from the Program for the Promotion of Alternative Sources
of Energy (PROINFA), set up by the Brazilian government early in this decade.
The construction of Praia Formosa made it necessary to build an additional 80
miles of power transmission lines that will send 416,678 megawatts an hour to
the electrical grid each year.
September 15,2009
Japan's Nuclear Rokkasho
Researched by Industrial Info Resources
(Sugar Land, Texas)--Japan's
nuclear
reprocessing plant at Rokkasho has suffered further delays and is now scheduled
for completion by October 2010. The delays have been caused by problems with the
vitrification line at the facility, which now needs to be cleaned and
re-inspected. Japan Nuclear Fuels Limited (JNFL) (Rokkasho), the operator of the
plant, has applied to the Ministry of Economy, Trade and Industry for permission
to change the project's plan.
The delay is one of several that have plagued the controversial site. The work
plan for the facility has been amended 14 times since the legislation for the
facility was passed, with problems with the vitrification process causing
several recent delays.
In the vitrification line, powdered and dried radioactive waste is mixed with
molten glass and then permanently stored in special flasks. JNFL intends to
begin cleaning the interior of the vitrification unit this month, paying special
attention to areas where liquid waste adhered to during earlier tests. After
completion of the cleaning process, the insulation resistance of the unit will
be restored and tested for effectiveness by December.
At the same time that the cleaning work is carried out, JNFL will inspect more
than 200 pieces of equipment that may have been contaminated by the nitric acid
contained in the waste used in the latest trial run, and replace parts as may be
required. In addition, the furnace used to produce the molten glass in the
vitrification process also will be inspected as some ceiling bricks had fallen
to the bottom. Any glass residue will be removed, and the furnace will be
re-inspected and prepared to restart the test run by July 2010.
In March 2008, JNFL filed a change to the scheduled work plan because of
problems with the glass-melting furnace. In November 2008, the government
required JNFL to submit a further report following a resumed test to produce
vitrified waste, which showed an increase of metal chaff accumulation on the
base of the furnace. The delays caused a reduction in the amount of fuel planned
to be processed in the first few years of operation. About 160 tons of fuel were
scheduled to be processed in the 12 months ending March 2010, but this plan has
been shelved. While 320 tons of fuel were to be processed over the subsequent 12
months, now only 80 tons of fuel would be processed during the period.
When fully operational, the Rokkasho plant will be able to process up to 800
tons of used nuclear fuel, equivalent to used fuel produced by 40 nuclear
reactors of 1,000 MW each. According to JNFL, this represents 80% of used fuel
produced by all of Japan's nuclear power stations. However, there is the far
greater problem of the 11,000 tons of spent nuclear fuel that is currently
stored onsite at Japanese power stations.
A number of organizations have voiced opposition to the Rokkasho plant,
including Greenpeace and the Stop Rokkasho project, claiming that the plant is
directly above an active geological fault and could cause an earthquake,
releasing highly toxic plutonium (present in the spent nuclear fuel at about
0.9%) from the plant. There also are concerns that the plant could increase the
danger to Japan from terrorist attacks.
The original 1989 estimates for the construction of the Rokkasho complex, which
includes the high-level nuclear waste facility, a uranium enrichment plant and a
low-level radioactive waste landfill, were about $6.9 billion. However, costs
have since escalated considerably, and total investment in the facility is now
estimated to be more than $20 billion.
September 15,2009
European Energy
Researched by
Industrial Info Resources (Sugar Land, Texas)--United Kingdom-based power
generation companies are increasingly looking to the opportunities provided by
the alternative power sector, and the U.K. government is hoping to entice more
activity in this area by launching a £7.2 million ($11.9 million) hydrogen fuel
cell competition.
The news comes in the same week that major energy companies and partners
announced plans to create an ambitious hydrogen infrastructure in Germany.
Energie Baden-Wuerttemberg AG (ETR:EBK) (EnBW) (Karlsruhe, Germany),
E.ON AG (OTC:EONGY) (Dusseldorf)
and Vattenfall AB (Stockholm, Sweden) have teamed up with Linde AG (ETR:LIN)
(Munich, Germany),
Daimler AG (NYSE:DAI)
(Stuttgart, Germany), OMV Aktiengesellschaft (WBAG:OMV) (Vienna, Austria),
Royal Dutch Shell plc (NYSE:RDS.A)
(The Hague, Netherlands), and NOW GmbH (The National Organization Hydrogen and
Fuel Cell Technology) (Berlin) to create a two-phase memorandum of understanding
to make hydrogen-fuelled cars a reality in Germany.
The U.K.'s Department of Energy and Climate Change (DECC) is proposing a
competition for up to £7.2 million of funding for companies to develop hydrogen
and fuel-cell technology. According to DECC, hydrogen and fuel cells have the
potential to drastically reduce carbon emissions because they only emit water
and heat as by-products. The energy conversion in fuel cells is more efficient
than those of other technologies, including traditional internal combustion
engines.
Energy and Climate Change Minister David Kidney said: "The U.K. has the right
combination of expertise, ingenuity and determination to bring hydrogen and fuel
cell technology to the global market. We're providing real help now to help
advance this technology in the UK, keeping us at the forefront of advanced green
manufacturing."
In Germany, Phase I will include the evaluation of options for an area-wide
rollout of hydrogen fuelling stations nationwide and the definition of a joint
business plan agreement, including an analysis of possible public support
measures. The goal is to install new hydrogen-fuelling stations by 2011. If
successful, Phase II will see the continuation of the rollout of fuelling
stations to support the introduction of hydrogen-powered vehicles by 2015.
"By means of hydrogen produced using power from renewable energy sources, we
will supply a low-emission fuel and ensure 'green' mobility," said Udo Bekker,
member of the board of Vattenfall AG. "In Hamburg we are already putting this
into practice. By the end of this year we will start work there on the
construction of Europe's biggest hydrogen filling station."
EnBW CEO Hans-Peter Villis said, "Regardless of whether vehicles are refuelled
with hydrogen or electricity, it remains a fact that these innovative drive
technologies will only be sustainable with a reliable infrastructure and only
with CO2-free electricity for hydrogen production or for recharging batteries.
EnBW will support both technologies, with its technological know-how in the
power generation field and its large proportion of CO2-free electricity."
In Ireland, the semi-state-owned electricity utility, Electricity Supply Board
(Dublin), has committed to rolling out a national infrastructure for charging
electric cars as part of a 10 billion euro push into the renewable energy
sector.
E.ON is already working with Ceramic Fuel Cells in the U.K. to develop micro
combined heat and power (mCHP) fuel cells for the budding micro-generation
market. They are working together to create a commercial mCHP product by 2012,
based on the Gennex fuel cell. E.ON predicts it could ship 100,000 of these
cells over a 6-year period.
Electricite de France (EPA:EDF) (Paris, France) has invested £700,000 ($1.15
million) in fuel cell specialists, Ceres Power, which is close to launching its
'electro chemical engine' for mCHP in the domestic marketplace. The company,
based in Crawley, Surrey, England, is part owned by Centrica and says its
product will use slightly more gas than a regular gas boiler but that it is
twice as efficient with regards to carbon emissions and is capable of generating
electricity as well.
September 14,2009
OKTA Refinery
Researched by
Industrial Info Resources (Sugar Land, Texas)--The 54,000-barrel-per-day (BBL/d)
OKTA
refinery
located in Skopje, Macedonia, is undergoing an overhaul. The plant is owned by
Hellenic Petroleum SA (ATH:ELPE) (Aspropyrgos, Greece) and operated by OKTA
(Skopje).
The OKTA refinery halted production September 1 for approximately 30
nonproduction days to perform inspection and cleaning of the Atmospheric
Distillation Unit, the 14,000-BBL/d Gasoline Hydrodesulfurization Unit, the
4,700-BBL/d Kero Hydrodesulfurization Unit, the 8,700-BBL/d Gas Oil
Hydrodesulfurization Unit, the 3,000-BBL/d Light Naphtha Isomerization Unit, the
10,200-BBL/d Catalytic Reformer, the 1,500-BBL/d Liquid Petroleum Gas Recovery
Unit, the Monoethanolamine Unit, and the 87-BBLd Sulfur Recovery Unit. All units
are expected to be back online September 30.
After performing the necessary inspection, authorities will decide which
maintenace work will be performed on the next overhaul, scheduled to take place
May 2010. The refinery, which began production in 1982, has a production site of
nine units and performs overhauls every year.
September 10,2009
Industrial Torc Global Website
I-Torc website will be down for
temporary maintenance. Contact Sales Support for all Technical and Sales
Assistance
September 10,2009
La Coruna Refinery - Spain
Researched by Industrial Info Resources
(Sugar Land, Texas)--The 119,000-barrel-per-day (BBL/d) La Coruña
Refinery , owned and operated by
Repsol YPF SA (NYSE:REP) (Madrid, Spain) usually performs programmed
shutdowns every four years in the Conversion Area and every five years in the
Distillation Area.
La Coruña Refinery is divided into two major areas: Conversion and Distillation,
each of them divided into different subareas. The Conversion Area experienced
its last general maintenance turnaround in 2008. The 50-nonproduction-day
planned shutdown started September 19 and finished November 10. As previously
mentioned, this area has a four-year period between each planned shutdown,
therefore the next shutdown is expected to occur in 2012. Turnarounds in this
area include several units such as the 32,000-BBL/d Fluid Catalytic Cracking
unit, the 19,000-BBL/d Vacuum 2 unit, and the Amine 4 unit, among others.
The Distillation Area had its last planned turnaround in 2006; consequently, the
next one is scheduled to take place in 2011. During these operations, units such
as the 50,000-BBL/d Crude 1 unit and the 18,800-BBL/d Vacuum 1 unit and the will
be serviced.
La Coruña Refinery is one of five refineries that Repsol operates in Spain.
September 09,2009
Petroleos de Venezuela S.A.
Researched by Industrial Info Resources
(Sugar Land, Texas)--Venezuela's state-owned
Petroleos de Venezuela S.A. (PDVSA) (Caracas) has been forced to import
gasoline due to expansion work and repetitive unplanned shutdowns at the
company's Fluid Catalytic Cracking units, which are in different locations
around the country.
The completion of the expansion project on the 51,000-barrel-per-day (BBL/d)
FCCU and 18,000-BBL/d Alkylation units at the 127,000-BBL/d refinery in El
Palito, Carabobo, which began on March 4 and involves the complete overhaul of
all the processing units, is to be completed by the end of September. The units
are set to be back online by mid-October. The refinery's 140,000-BBL/d Crude and
the 71,000-BBL/d Vacuum and BTX units have been online since June 10.
On August 27, the company was forced to shut down the 130,000-BBL/d Flexicracker
unit at its 635,000-BBL/d Amuay refinery due to tubes leaks. As a result, the
Alky unit is being kept offline, while the 85,000-BBL/d Crude 1 and
120,000-BBL/d Crude 3 have been placed into hot-oil circulation. The FCC at this
refinery previously had been shut down for 11 days in early August due to issues
with the reactor.
Completion of the ongoing expansion work at the Cardon Refinery's FCCU and
Alkylation units has been delayed several times this year. Maintenance began in
mid-February 2008 on the 11,000-BBL/d Alkylation unit to increase the unit's
capacity from 1,500 tons per day to 2,400 tons per day. The FCCU project, which
began in August 2008, aims to expand the unit's capacity from 11,000 tons per
day to 12,800 tons per day, along with several other processing units. The units
originally were scheduled to restart in mid-January, and again in March and
April; however, authorities have been informed that the restarts again have been
rescheduled, now to mid-October because of the lack of workforce and inclement
weather.
The 52,000-BBL/d FCCU at the Willemstad Isla, Curacao, refinery remains offline
since August 27 after all the processing units at the facility were forced to
shut down due to an unexpected power outage. The 45,000-BBL/d Crude 2 A, the
8,000-BBL/d Feed Crack 1 and the Alkylation units also are kept offline.
Separately, the cat cracker's fractionator is having its catalyst removed. Main
authorities expect to restart the offline units by September 5.
September 08,2009
StatoiHydro - Norway
Researched by Industrial Info Resources (Sugar Land, Texas)--StatoilHydro
ASA (NYSE:STO) (Stavanger, Norway) is
successfully advancing with the Karsto's Expansion Project 2010, with 35% of the
liquefied natural gas
(LNG)-related project construction complete.
The project's main objective is to comply with enviromental agreements and new
policies, which involve the control of CO2 emissions and ensure the supply of
LNG in the region, by revamping the oldest facilities of the existing plant.
The project includes two new sub-projects, including four metering stations for
loading from tanks to carriers, and replacement and equipment for mixing gas
between the Statpipe and Asgard pipelines.
The main objective of these facility installations is to ensure the right CO2
level in the plant. On August 24,
KBR Incorporated (NYSE:KBR)
(Houston, Texas), a U.S.-based engineering construction and services company,
announced that subsidiary M.W. Kellogg Limited had been awarded two contracts
which cover site preparation, foundations and road work in connection with the
implementation of these two new sub-projects.
The Karsto processing plant, located in the north of Stavanger and operated by
Gassco AS, processes and transports gas and condensate (light oil) from major
regions of the Norwegian continental platform.
September 07,2009
China Begins Construction
Researched by
Industrial Info Resources (Sugar Land, Texas)--Following the successful
commissioning of the southeast Shanxi-Nanyang-Jingmen 1,000-kilovolt (KV)
transmission line, the
first 1,000-kV ultra-high-voltage AC demonstration transmission project in
China, the
National Development and Reform Commission
(NDRC) approved the second batch of ultra high voltage transmission projects
recently, the NDRC announced on August 31.
Among the second batch of projects is the 750-kV Fenghuang-North
Urumuqi-Turpan-Hami transmission project in Xinjiang and several 500-kV
transmission projects in the Inner Mongolia region and Yunnan. The 750-kV
transmission project in Xinjiang involves the construction of 4 transformer
substations with a total capacity of 5,500 megavolt-amperes and 1,301 kilometers
of transmission line.
The $848 million transmission line from southeast Shanxi to Jingmen via Nanyang
was officially commissioned in January this year, which marks the beginning of
the construction of an ultra high voltage grid in China. However, this
transmission line is located within central China, which doesn't involve the
nation's strategy of transmitting power from west to east. Approval of the
second batch of ultra high voltage transmission projects will directly promote
the west-to-east transmission program into the ultra high voltage age.
The State Grid will invest more than $14.7 billion for the construction of ultra
high voltage transmission projects in next three to four years. It is expected
that the total investment of the State Grid in ultra high voltage transmission
projects will surpass $87.7 billion by 2020, according to Yinbiao Shu, Vice
President of the State Grid Corporation of China (Beijing), at 2009
International Conference on UHV Power Transmission held in Beijing on May 21.
As reported, China's power consumption is expected to reach 7.7 trillion
kilowatt-hours in 2020, about twice the current value. China's coal, water and
wind energies are mainly concentrated in the western region, long-distance and
large-scale power transmission from the west to the east will be essential.
Construction of the ultra high voltage grid will greatly reduce line loss,
improve transmission efficiency and reduce costs.
September 04,2009
BP Oil Discover
People in the oil industry are
celebrating quite a discovery.
Drillers in the Gulf of Mexico
have tapped into one of the deepest wells in the world. Oil producer BP says it
has found new oil in its Gulf of Mexico Fields estimated at about four to six
billion barrels worth.
The new oil well is more than
35,000 feet deep. It's expected to rank among the largest petroleum discoveries
in the United States.
September 03,2009
Rheinland Godorf Refinery
Researched by Industrial Info Resources
(Sugar Land, Texas)--The 195,300-barrel-per-day (BBL/d) Rheinland Godorf
Refinery (North), located
in Germany and owned and operated by
Shell Deutschland Oil GmbH
(Hamburg, Germany), is undergoing a shutdown on several processing units. Shell
Deutschland Oil GmbH is a subsidiary of
Royal Dutch Shell plc (NYSE:RDS.A)
(The Hague, Netherlands).
The plant, which began operations in 1957, is divided into three production
areas: MMO (Maintenance, Manufacture, Operations), MMK (Maintenance,
Manufacture, Conversion) and MME (Maintenance, Manufacture, Energie).
Rheinland Godorf Refinery halted production on August 31 for 26 days to perform
cleaning and maintenance work on the MMO and MME areas. The shutdown will affect
the Crude Distillation 1, the Vacuum 1, the Vacuum 2, the HDS (Gasoil), the HDS
(Naphtha), the Platformer, the Thermal Gas Oil and the Bitumen Plant, among
others. Units are expected to resume operations on September 25. For more
details, view related July 24, 2009, news article -
Germany's Rheinland Godorf Refinery Offline for
Maintenance Turnaround.
September 03,2009
India's NPCIL and South
Korea's KEPCO
Researched by Industrial Info Resources (Sugar Land, Texas)--Nuclear
Power Corporation of India (NPCIL) (Mumbai),
India's
nuclear power generating
company, has signed a memorandum of understanding with
Korea Electric Power Corporation (NYSE:KEP)
(KEPCO) (Seoul, South Korea) to conduct joint nuclear power technology studies.
The agreement will include the technology licensing and construction of APR-1400
nuclear reactors. The deal also allows for assistance in knowledge transfer of
nuclear power technology; maintenance and operations of nuclear power plants;
and nuclear fuel and equipment supply.
Earlier, NPCIL signed similar deals with
Westinghouse Electric LLC
(Monroeville, Pennsylvania),
GE-Hitachi Nuclear Energy Incorporated
(Wilmington, North Carolina), and
Areva SA (EPA:CEI)
(Paris, France). The cooperation agreement with KEPCO is expected to open doors
for South Korea in India's nuclear power sector. The agreement with South Korea
is the fourth nuclear power cooperation agreement signed by NPCIL this year.
International energy firms are focusing on developing nuclear power in India
after the Nuclear Suppliers Group lifted the 34-year nuclear trade embargo.
KEPCO is emerging as a leading player in the global development and supply of
nuclear reactors. The company is also offering its APR-1400 Pressurized Water
Reactor, developed from Westinghouse units, to Belarus, Poland, as well as the
Middle East and North Africa. Recently, KEPCO acquired a 17% stake in uranium
supplier
Denison Mines Corporation (TSX:DNN)
(Toronto, Ontario) for $68 million. The deal is expected to provide some relief
to South Korea's growing nuclear fuel demand, which has a present requirement of
4,000 tons per year of uranium; Denison Mines produces around 1,000 tons per
year.
South Korea houses a production facility for APR-1400 at Shin Kori. The country
is planning to set up five more manufacturing units by 2015. It has 20 operating
nuclear power reactors, and plans to build four other models. South Korea, which
derives about 40% of its energy needs from the nuclear power sector, has
targeted 27,300 megawatts (MW) of installed nuclear power generation capacity by
2020.
India has 17 operating nuclear power plants, generating about 4,120 MW of power
annually. Three reactors with combined capacity of 2,660 MW are under
construction. India has envisaged a three-pronged nuclear power development
initiative. This includes construction of 28 new reactors, which, on commencing
operations, will achieve the target of 40,000 MW of additional power generating
capacity by 2020. Contribution of nuclear power to the national grid has been
targeted at about 25% by 2050. NPCIL also has commissioned eight 700-MW
Pressurized Heavy Water Reactors with indigenous technology. The company is also
planning to construct nuclear reactors with capacities of 1,000 MW and more with
international cooperation. Despite being a late entrant in this sector, India is
expected to attract domestic and international nuclear power investments of more
than $27 billion in the next 15 years.
September 2, 2009
Kuwait National Petroleum
Researched by
Industrial Info Resources (Sugar Land, Texas)--According to reports published by
the Arabic daily newspaper Al-Watan, state-run Kuwait National Petroleum
Company (KNPC) (Safat, Kuwait) may retender contracts to set up the Al Zour
refinery near the
Kuwait-Saudi Arabia
border, after canceling the earlier tender issued in March 2009 because of
parliamentary opposition. The paper mentions that the retendering process is
likely to start after Kuwait's Supreme Petroleum Council makes an announcement
about the project. A consultancy firm is likely to be hired to assess the
project under the supervision of the Central Tenders Committee. However, most
sources view the project as cancelled.
The 615,000-barrel-per-day (BBL/d) project was first announced in 2005 when
Kuwait's refining capacity was 900,000 BBL/d. The original cost estimate of the
project was about $6 billion, but this soon increased to an unexpectedly high
$15 billion following the rapid increase in demand and refining capacity
worldwide. The refinery was scheduled to begin operations in 2012 and would have
increased the country's refining capacity to 1.4 million BBL/d combined with
upgrades to two other refineries. The Al Zour refinery, when completed, would
have been the world's fourth-largest refinery and would have supplied low-sulfur
fuel oil to the nation's power plants.
KNPC proceeded with front-end engineering and design (FEED) work and the
selection of project managers and contractors. Five companies were awarded
engineering, procurement and construction (EPC) contracts worth $8.4 billion in
May 2008. However, the project faced a great deal of political opposition.
Lawmakers alleged several tender violations, including the award of a $2 billion
project management contract to
Fluor Corporation (NYSE:FLR)
(Irving, Texas) without a tender. A few members of parliament are believed to
have questioned the feasibility of the project and the procedures that were
followed in awarding the contracts. In March 2009, KNPC informed the companies
that had secured contracts that the tender had been cancelled, although the
decision to set up the project had not been cancelled. KNPC cited the fact that
an independent body had declared that the project was unfeasible as reason for
the cancellation of the tender.
The cancellation of the tender came as a shock to all concerned parties,
especially as $1 billion had already been spent on the project. Cancellation
charges could raise this amount, bringing to prominence the immense difficulties
in making decisions about such large-scale projects.
In May 2008, EPC contracts were awarded to a consortium of JGC Corporation
(TYO:1963) (Tokyo, Japan) and GS Engineering and Construction Corporation
(SEO:006360) (Seoul, South Korea), which was awarded a $4 billion contract to
provide the main manufacturing units of the refinery. SK Energy Company Limited
(SEO:096770) (Seoul) was awarded a $2 billion contract to provide the refinery's
subsidiary units. Daelim Industrial Company Limited (SEO:000210) (Seoul) was
awarded a $1.184 billion contract to provide the refinery project with tanks.
Hyundai Engineering and Construction Company (SEO:000720) (Seoul) was awarded a
$1.12 billion contract to equip the project with the necessary offshore
facilities. All of these contracts remain cancelled.
Income from oil accounts for 95% of the public revenues of Kuwait. According to
2008 estimates, Kuwait had a refining capacity of about 2.2 million BBL/d and
about 100 billion barrels of oil reserves. There appears to be numerous doubts
about the accuracy of the quantity of oil reserves in the country.